Forceman Ridge Waste Management Facility - Phase 1B Cell Construction
Share Forceman Ridge Waste Management Facility - Phase 1B Cell Construction on FacebookShare Forceman Ridge Waste Management Facility - Phase 1B Cell Construction on TwitterShare Forceman Ridge Waste Management Facility - Phase 1B Cell Construction on LinkedinEmail Forceman Ridge Waste Management Facility - Phase 1B Cell Construction link
Forceman Ridge is an engineered landfill, located between Terrace and Kitimat on Highway 37, consisting of an engineered and composite-lined landfill, a state-of-the-art compost facility, septage facility and a five-step leachate treatment system. Landfill operations commenced at Forceman Ridge in November 2016. The facility serves a population of over 20,000 people from Terrace, Thornhill, and Electoral Area C (Greater Terrace) of the Regional District. Forceman Ridge also services the LNG Canada project in Kitimat.
What is Phase 1B and why is it under construction?
The initial landfill design for Forceman Ridge consisted of seven different phases, including Phases 1A through 1F and Phases 2-7. Phase 1A is currently in operation and nearing its capacity. To provide additional capacity and ensure uninterrupted operation of the landfill, Phase 1B cell construction was prioritized and is now in progress. Phase 1B is located to the west of Phase 1A - view aerial photo.
What is the construction timeline?
The construction timeline consists of two stages. Stage 1 of Phase 1B cell construction was completed in fall 2022 and Stage 2 is to be complete in summer/fall 2023. See the Project Timeline section of this page for more information or contact the Project Manager if you have any questions.
Early construction photo - August 18, 2022
Forceman Ridge is an engineered landfill, located between Terrace and Kitimat on Highway 37, consisting of an engineered and composite-lined landfill, a state-of-the-art compost facility, septage facility and a five-step leachate treatment system. Landfill operations commenced at Forceman Ridge in November 2016. The facility serves a population of over 20,000 people from Terrace, Thornhill, and Electoral Area C (Greater Terrace) of the Regional District. Forceman Ridge also services the LNG Canada project in Kitimat.
What is Phase 1B and why is it under construction?
The initial landfill design for Forceman Ridge consisted of seven different phases, including Phases 1A through 1F and Phases 2-7. Phase 1A is currently in operation and nearing its capacity. To provide additional capacity and ensure uninterrupted operation of the landfill, Phase 1B cell construction was prioritized and is now in progress. Phase 1B is located to the west of Phase 1A - view aerial photo.
What is the construction timeline?
The construction timeline consists of two stages. Stage 1 of Phase 1B cell construction was completed in fall 2022 and Stage 2 is to be complete in summer/fall 2023. See the Project Timeline section of this page for more information or contact the Project Manager if you have any questions.
Forceman Ridge Waste Management Facility - Phase 1B Cell Construction has finished this stage
A Request for Proposals for design and consulting services was posted on BC Bid. The Regional District received two bids and after evaluation, the project was awarded to GHD Ltd in May 2022.
Procurement for Construction Services
Forceman Ridge Waste Management Facility - Phase 1B Cell Construction has finished this stage
A tender construction contract was posted on BC Bid. The Regional District received five bids and after evaluation, the construction contract was awarded to IDL Projects Inc. in July 2022.
Mobilization and Pre-construction Meeting
Forceman Ridge Waste Management Facility - Phase 1B Cell Construction has finished this stage
The contractor started mobilization and site set up on August 8 and a pre-construction site meeting was held on August 12.
Stage 1 Construction
Forceman Ridge Waste Management Facility - Phase 1B Cell Construction has finished this stage
Stage 1 of Phase 1B cell construction was completed in fall 2022.
Stage 2 Construction
Forceman Ridge Waste Management Facility - Phase 1B Cell Construction is currently at this stage
Following a pause in construction over winter 2022/2023, Stage 2 of Phase 1B cell construction is scheduled to commence in spring 2023 and be completed by the end of the summer/fall.